Howest University Campus, Kortrijk, Belgium

  • Byggnadstyp:
  • Utbildning & Kultur
Hel skärm Stänga

For the new university campus of Howest in Kortijk, Peikko's DELTABEAM® solution was chosen to be able to create slim floors and keep a lot of flexibility in the layout.

Peikko delivered more than 1,200 meters of DELTABEAM® composite beams for this project.  

For DELTABEAM® excellent preparation is needed and the engineering is very important. When the engineering is finalized, the base for a very fast building system is established. At the same time there are benefits for the installation of HVAC, since there is a lot more usuable height available when working with DELTABEAM®.

Tom Verplancke, site manager for Monument Vandekerckhove

Fakta om projektet

Våningar:
5
Utvecklare:
Howest, Hogeschool West-Vlaanderen
Byggentreprenör:
Monument Vandekerckhove
Huvudkonstruktör:
ABDM
Arkitekt:
RAU
Leveransår:
2018
Färdigställandeår:
2019

Lösningar vi tillhandahöll